We pride ourselves on our quality of work and friendly approach with our clients and suppliers. As a company we are recognised as trusted traders by the local neighbourhood watch and the police. Please see below our team at work. During the months of December 2017 to February 2018 – please click on any of the pictures to enlarge. Keep up to date with all our current projects on Facebook

20 November 2017 – Foundation work has begun 

21st November 2017 – Our faithful glazier has sorted out a problematic door for us. And the stumps have been ground down on another job, and we have been having a muddy time.

22nd November – Foundations passed, i was going to chuck the earth back at one stage 

23rd November 2017 – Foundations done 

27th November 2017 – Today’s progress, all flowing well inc. 💩💩

28th November 2017 – Shingle down and filling in, for now. Dirt from back to front ready for collection. 🐧🐧🐧 cold

6th December 2017 – Four and a half grab truck loads of dirt later. 13 ton of type 1 in. Looking a lot more tidy 

12th December 2017 – Now going in the right direction. Up!

14th December 2017 – Weather has been against us as well as those winter colds. But we are now up and running again.

16th December 2017 – Progress this week.

18th December 2017 – Ready for first lift.

20th December 2017 – And delivery is in ready for the morning 

21st December 2017 – Both jobs going full steam ahead. Back on schedule phew!

30th December 2017 – Full steam ahead…

2nd January 2018 – Guys have started piling.

3rd January 2018 – So this little gismo goes back home today.

5th January 2018 – Piles are done, just the ring beam to be done. Second lift on other job.

11th January 2018 – Boys have been working on this. Meanwhile, home and a showered dog phew! Not too fond of a hairdryer 😂

12th January 2018 – Guys are doing great on the groundworks, and the third lift is in place.

14th January 2018 – Great work x

15th January 2018 – Hard ground ! Hopefully more progress tomorrow minus rain. We need to get cracking on this 😉

19th January 2018 – Progress to date on both jobs. Pilers should be finished Monday ready for us to do block and beams etc. Hopefully brickies in doing the remainder of the first job and start of the next 😎 we welcome details of trades people to place on our books. We do prefer local traders as this is something we believe to be the done thing (looking after each other locally).

22nd January 2018 – Both jobs going well 😃

24th January 2018 – Awaiting beams sometime thursday which will need to go on the drive. Then we can get in and put them in place.

26th January 2018 – Materials in and ready to go.

30th January 2018 – Block & Beamed

2nd February 2018 – My effort on the blue moon pic 😜 and our progress to date.